Bonus Pool Plan
The General Contractor will establish a Bonus Pool program offering every Subcontractor a cash incentive for achieving the Project Goals outlined below.
  1. The Project Goals are:
    1. The project is completed by the Completion Date;
    2. There are no unresolved claims by any subcontractor for interference or damage by any other subcontractor or contractor; and
    3. There have been no accidents which have caused more than {WorkDaysLost.#} work days to be lost.
  2. If all of the Project Goals are achieved, the General Contractor will pay to each Subcontractor, in addition to each Subcontractor’s normal compensation, a bonus of {BonusToSubcontractor.%} of the Subcontractor’s adjusted contract sum.