Bonus Pool Plan
The General Contractor will establish a Bonus Pool program offering every Subcontractor a cash incentive for achieving the Project Goals outlined below.- The Project Goals are:
- The project is completed by the Completion Date;
- There are no unresolved claims by any subcontractor for interference or damage by any other subcontractor or contractor; and
- There have been no accidents which have caused more than {WorkDaysLost.#} work days to be lost.
>If all of the Project Goals are achieved, the General Contractor will pay to each Subcontractor, in addition to each Subcontractor’s normal compensation, a bonus of {BonusToSubcontractor.%} of the Subcontractor’s adjusted contract sum.>